IPT was engaged to deliver spool detailing, fabrication coordination, QA/QC management and logistics support for the D&E Stage 2 SFN (B4 Interconnecting) project, a major data centre infrastructure development.
Over a 12-month period, the project expanded significantly beyond its original scope, requiring close collaboration between drafting, fabrication, QA and delivery teams to accommodate ongoing design changes and evolving site requirements. What began as a 4,420-spool package ultimately grew to 11,123 fabricated and delivered spools.
Working across fabrication facilities in Melbourne, Shepparton and Sydney, IPT coordinated 139 separate deliveries while maintaining full spool traceability, quality assurance and programme compliance throughout the project lifecycle. The team also successfully navigated multiple factory relocations without disrupting production schedules or delivery commitments.
By project completion, IPT had delivered more than 11,000 spools and managed approximately 33,180km of transport, demonstrating our ability to scale rapidly, adapt to change and deliver complex fabrication packages for Australia’s growing data centre sector.
Project Highlights
• 11,123 spools fabricated and delivered
• 139 deliveries coordinated across three fabrication hubs
• 33,180km of transport managed
• 100% spool-level drafting, tracking and QA control
• Delivered within 12 months of first drawing issue
• Multiple facility relocations completed without impacting programme delivery